USACE continues the Hawaii Wildfires Recovery Mission
The U.S. Army Corps of Engineers continues work on the critical public facility as part of the Hawaii Wildfires Recovery mission. Contractors will place 337 modular units to form ten large and 20 small classrooms. Besides the classrooms, the campus will include three restrooms, one administration building, one learning center, and one combination dining and food service center. As of Jan. 8, 2024, 300 units are on site and ready for placement. The modular school is a temporary replacement for the King Kamehameha III Elementary School, which served the students of Lahaina since 1913.